Project Description
Construction of a 25,000 SF, 2 story addition at AY Jackson Secondary School. Constructed of conventional structural steel on concrete foundations. Facade is a combination of steel siding, composite, curtain walls and brick veneer.
Please be advised the following scopes of work are prequalified per section 00 21 00.01 :
Electrical
Data Cabling
Roofing
Asphalt Paving
Abatement
SCHEDULE: Work at the site is to commence upon contract award. Occupancy of the building is required by November 27, 2026.
Please send all questions in writing to estimating@frecon.ca
Trades
- Division 02 - Exisiting Conditions
- Demolition
- Hazardous Material Removal
- Division 03 - Concrete
- Concrete Finishing
- Concrete Forming & Accessories
- Concrete Reinforcing
- Division 04 - Masonry
- Masonry
- Division 05 - Metals
- Metal Fabrications
- Stainless Fabrications
- Structural Steel
- Division 06 - Wood, Plastics, Composites
- Architectural Woodwork
- Division 07 - Thermal & Moisture Protection
- Aluminum Panels
- Caulking
- Fire Proofing
- Fire stopping
- Membrane Roofing
- Metal Siding & Roofing
- Roof Anchors
- Spray on Insulation
- Division 08 - Openings
- Aluminum Windows, Curtain Wall, Entrances
- Doors and Frames
- Hardware
- Operators
- Skylights
- Wood Doors
- Division 09 - Finishes
- Drywall
- Epoxy
- Flooring
- Hardwood Sports Flooring
- Painting & Wallcoverings
- Division 10 - Specialties
- Chalk & Tack
- Lockers
- Signs
- Stage Drapery
- WA
- Window Film
- Division 21 - Fire Suppression
- Fire Suppression
- Division 22 - Plumbing
- Plumbing
- Division 23 - HVAC
- HVAC
- Division 26 - Electrical
- Electrical
- Division 27 - Comms
- Comms
- Division 31 - Earthwork
- Earthwork
- Division 32 - Exterior Improvments
- Landscaping
- Paving & Curbs
- Site Furnishings
- Division 33 - Utilities
- Utilities